Project Update - August 2023
With the completion of Stage 2A in July 2023, the construction for the entire Heritage Valley District Park project is nearing completion.
The new sports fields will not be available until spring 2024 to allow for seed germination.
The new Catholic school (Father Michael McCaffery) is under construction by Alberta Infrastructure on the northwest side of Heritage Valley District Park. To accommodate construction of the school, a temporary access road and a laydown area within the park is required for a duration exceeding the parameters of the development of the district park. As a result, an additional stage of development will be required to complete the park once the temporary access road and laydown is no longer needed. Construction for Stage 2B will be initiated upon completion of the school.