Project Update - September 2025
Construction on Phase 2 of Imagine Jasper Avenue is underway and includes Jasper Avenue between 114 Street and 124 Street.
Imagine Jasper includes 2 lanes of motor vehicle traffic in each direction, shorter pedestrian crossing distances at each street along Jasper Avenue, wider sidewalks, landscaping, benches and bike racks.
The design is similar to what was recently constructed on Jasper Avenue between 109 Street and 114 Street.
Phase 2 construction is anticipated to be completed over three years:
- Year 1 (2025) - 114 Street to 117 Street
- Year 2 (2026) - 117 Street to 121 Street
- Year 3 (2027) - 121 Street to 124 Street
Construction will be paused during the winter months to minimize traffic disruptions.
Read the Imagine Jasper Avenue Spring Newsletter for more information.
Imagine Jasper Avenue Phase 2 Designs (12MB)