Construction Update - August 2025
It’s the first year of Overlanders and Homesteader Neighbourhood Renewal and construction started in April! Work will consist of reconstruction and paving of the roads, removal and replacement of public sidewalk, curb, gutter and street lighting.
Sidewalk installation is ongoing on the north side of Huffman Crescent and Humberstone and the west side of Hughes Road. Road reconstruction has started on the east side of William Hustler Crescent. Street light relocations started in July and continue.
Drainage work for the 2025 scope is nearly complete.
Current active work areas include:
- Road reconstruction from 148 to 84 of William Hustler Crescent
- Road reconstruction from 208 to 152 on Humberstone Road
- West side of Hughes Road from Hermitage Road to Huffman Crescent Road
- North side of Huffman Crescent from 372 to 414 Huffman Crescent Road
Check out the links below to prepare for construction:
The City of Edmonton and EPCOR are working together to construct Low Impact Development (LID), which will help with stormwater retention and help mitigate flooding.
If you live in the 2025 construction area, please watch your mailbox for construction bulletins that will provide more information along with details on landscaping and access. All residents and business owners are asked to access their homes and businesses through the back entrances and alleys, where possible, during construction. If no alley access is available and/or you have special access requirements (such as DATS or a temporary access ramp to the front of your home), please contact the construction Project Manager, Jamal Mohamed, 780-496-4055, to coordinate.
Construction in Overlanders began in spring 2025 and is expected to take 2 years (planned completion fall 2026).