Collector Renewal construction is underway on 132 Avenue between Fort Road and 127 Street.

Sign up for the Neighbourhood Renewal newsletter to receive news and updates on 132 Avenue Renewal.

Project Areas

132 Avenue West (97 Street to 127 Street)

Construction Update - May 2026

It’s the fourth year of Collector Renewal on 132 Avenue and construction is underway. Work will consist of reconstruction and paving of the roads, removal and replacement of public sidewalk, curb, gutter and street lighting. 

Crews are currently working from 121 Street to 126 Street and from 127 Street to 128 Street. Please view this scope map to see the 2026 construction area.

For those who live in the 2026 construction area (specifically from 121 Street to 127 Street), the remaining landscaping work is scheduled to start at the same time as this year’s construction. Landscaping work is highly dependent on weather and sod availability.

The City of Edmonton and EPCOR are working together to construct Low Impact Development, which will help with stormwater retention and help mitigate flooding.

Please watch your mailbox for construction bulletins that will provide more information along with details on landscaping and access. All residents and business owners are asked to access their homes and businesses through the back entrances and alleys, where possible, during construction. If no alley access is available and/or you have special access requirements (such as DATS or a temporary access ramp to the front of your home), please contact the Project Manager at 780-496-4055, to coordinate.

132 Avenue East (Fort Road to 97 Street)

Construction Update - May 2026

It’s the third year of 132 Avenue Renewal East and construction is underway. Work will consist of reconstruction and paving of the roads, removal and replacement of public sidewalk, curb, gutter and street lighting. Please view this scope map to see the 2026 construction area.

Crews are currently excavating on the south side of 132 Avenue between 90 Street and 88 Street, as well as on the north side between 86 Street and 85 Street. One lane of traffic is maintained in both directions.132 Avenue between 90 Street and 82 Street will be fully closed at the end of June.

2026 construction is taking place in front of St. Matthew, St. Cecilia and Archbishop O’Leary schools. Two-way traffic with one lane in each direction will be maintained until the end of June.

During construction, staff, students and parents/guardians will still be able to access these schools via 132 Avenue. More information, including accessible pick-up/drop-off zones, is available in the bulletins:

For those who live in the 2025 construction area, specifically from 66 Street to Delwood Road, any remaining landscaping work is scheduled to start at the same time as this year’s construction. Landscaping work is highly dependent on weather and sod availability.

The City of Edmonton and EPCOR are working together to construct Low Impact Development, which will help with stormwater retention and help mitigate flooding. 

Please watch your mailbox for construction bulletins that will provide more information along with details on landscaping and access. All residents and business owners are asked to access their homes and businesses through the back entrances and alleys, where possible, during construction. If no alley access is available and/or you have special access requirements (such as DATS or a temporary access ramp to the front of your home), please contact Project Manager Alban Ukshini 780-496-4055, to coordinate.

Construction in 132 Avenue West began in spring 2023 and is expected to take 4 years (planned completion fall 2026). Construction on 132 Avenue East began in spring 2024 and is expected to take 4years (fall 2027). The entire 132 Avenue Collector Renewal project (Fort Road to 127 Street) is expected to take 5 years (completion in fall 2027).

Check out the links below to learn more about 132 Avenue Collector Renewal:

The What We Decided Report describes the final designs for 132 Avenue Renewal, including when and how the City used policy and program information, public engagement input and technical requirements to make project decisions.

Building great neighbourhoods graphic

132 Avenue Renewal

Sign up to receive news and updates on the Collector Renewal project happening along 132 Avenue.

Project History

Construction Update - November 2025

132 Avenue West (97 Street to 127 Street)

The 2025 construction season was a success and we completed all planned construction including the reconstruction of roads, new sidewalks, curbs and gutters, Low Impact Development (LID) facilities, the new active transportation network and installed new street lights between 113 A Street to 121 Street.

132 Avenue East (Fort Road to 97 Street)

2025 construction began in April and finished the first week of November. The 2025 construction season was a success and we completed all planned construction including the reconstruction of roads, new sidewalks, curbs and gutters, Low Impact Development (LID) facilities, the new active transportation network and installed new street lights between 66 Street and Delwood Road. 

Construction Update - October 2025

132 Avenue West (97 Street to 127 Street)

The third year of 132 Ave Renewal West construction is underway! Work will consist of reconstruction and paving of the roads, removal and replacement of public sidewalk, curb, gutter and street lighting.

132 Avenue between 113 A Street and 121 Street remains closed as construction is ongoing. 132 Avenue is scheduled to reopen at the end of October.

132 Avenue East (Fort Road to 97 Street)

132 Avenue between 66 Street and 72 Street has reopened to the public. The remaining closed section between 72 Street to west of Delwood Road is scheduled to open at the end of October. Please follow all signage and detours.

Construction Update - June 2025

132 Avenue West (97 Street to 127 Street)

The third year of 132 Ave Renewal West construction is underway! Work will consist of reconstruction and paving of the roads, removal and replacement of public sidewalk, curb, gutter and street lighting.

121 Street to 115 Street is currently closed. Starting June 16, that will extend to include 115 Street to 113 A Street.

This year, the majority of construction will take place from 113 A Street to 121 Street. Please view this scope map to see the 2025 construction area. Work will also happen in the commercial area along 113 A Street.

For those who live in the 2025 construction area, specifically from 113 A Street and 121 Street, the remaining landscaping work is scheduled to start at the same time as this year’s construction. Landscaping work is highly dependent on weather and sod availability.

The City of Edmonton and EPCOR are working together to constructLow Impact Development (254.87 KB), which will help with stormwater retention and help mitigate flooding.

If you live in the 2025 construction area, please watch your mailbox for construction bulletins that will provide more information along with details on landscaping and access. All residents and business owners are asked to access their homes and businesses through the back entrances and alleys, where possible, during construction. If no alley access is available and/or you have special access requirements (such as DATS or a temporary access ramp to the front of your home), please contact the Construction Project Manager, Alban Ukshini, 780-496-4055, to coordinate.

Construction on 132 Avenue West began in May 2023 and is anticipated to be complete in 4 years (fall 2026). The entire 132 Avenue Collector Renewal project (Fort Road to 127 Street) is expected to take 5 years (completion in fall 2027). 132 Avenue Renewal West is progressing on time and on budget.

132 Avenue East (Fort Road to 97 Street)

The second year of 132 Avenue Renewal East is underway. Work will consist of reconstruction and paving of the roads, removal and replacement of public sidewalk, curb, gutter and street lighting.

There are currently two sections of the project that are closed: 66 Street to 69 Street and 72 Street to Delwood Road.

2025 construction will impact access around St. Vladimir School and Daycare. View construction impacts and detours.

This year, the majority of construction will take place from 66 street to 82 street. Please view this scope map to see the 2025 construction area. Work will also happen in the commercial areas along 72 Street and 82 Street.

For those who live in the 2024 construction area, specifically from Fort Rd to 66 street, the remaining landscaping work is scheduled to start at the same time as this year’s construction. Landscaping work is highly dependent on weather and sod availability.

The City of Edmonton and EPCOR are working together to construct Low Impact Development (254.87 KB), which will help with stormwater retention and help mitigate flooding.

If you live in the 2025 construction area, please watch your mailbox for construction bulletins that will provide more information along with details on landscaping and access. All residents and business owners are asked to access their homes and businesses through the back entrances and alleys, where possible, during construction. If no alley access is available and/or you have special access requirements (such as DATS or a temporary access ramp to the front of your home), please contact the Construction Project Manager, Bin Pllana, 780-446-7037, to coordinate.

Construction on 132 Avenue West began in May 2023 and is anticipated to be complete in 4 years (fall 2026). The entire 132 Avenue Collector Renewal project (Fort Road to 127 Street) is expected to take 5 years (completion in fall 2027). 132 Avenue Renewal West is progressing on time and on budget.

Construction Update - November 2024

132 Avenue West (97 Street to 127 Street)

The 132 Avenue West Collector Renewal project has wrapped up for the 2024 construction season! 

2024 construction began in May and was finished the third week of October. The 2024 construction season was a success and we completed all planned construction including the reconstruction of roads, sidewalks, curbs and gutters, Low Impact Development installation, bike lanes, signals and new street lights in the following areas:  

  • 132 Avenue - 97 Street to 101 Street
  • 132 Avenue -107 Street to 113A Street

There are some naturalized turf areas along the boulevard that were not completed from 107 Street to 113A Street. The outstanding work will resume once the weather warms up in early May. The landscape subcontractor will be completing the topsoil and sod placement. By waiting until spring, the sod is more likely to establish. 

Year 3 of construction along 132 Avenue West will resume in the first week of May 2025, weather permitting. The planned scope for 2025 will include 113A Street to 122 Street. Prior to work resuming, construction notifications will be delivered to impacted residences. 

Thank you for your patience and understanding as we completed another successful year of construction. Construction on 132 Avenue West began in May 2023 and is anticipated to be complete in 4 years (fall 2026). The entire 132 Avenue Collector Renewal project (Fort Road to 127 Street) is expected to take 5 years (completion in fall 2027).

The 132 Avenue West project is progressing on time and on budget.

132 Avenue East (Fort Road to 97 Street)

132 Avenue East Collector Renewal construction has wrapped up for the 2024 construction season! 

2024 construction began in June and was finished the last week of October. The 2024 construction season was a success and we completed all planned construction including the reconstruction of roads, sidewalks, curbs and gutters, bike lanes, shared-use pathways, continuous crossings, landscaping, corner store business upgrades and new street lights along 132 Avenue between Fort Road and 66 street. 

There are some landscape elements such as shrubs, perennials and naturalized turf that were not completed in 2024. The outstanding work will be completed when construction resumes in 2025. Parts of the 2024 construction area may also require sod. Once the weather warms up, typically in early May, the landscape subcontractor will be completing the topsoil and sod placement. By waiting until spring, the sod is more likely to establish. 

132 Ave East Renewal work will resume between 66 Street to 82 Street in the second week of April 2025, weather permitting. Prior to work resuming, construction notifications will be delivered to impacted residences. 

Thank you for your patience and understanding as we completed the first year of renewal construction on 132 Avenue East. 132 Avenue East Collector Renewal construction began in June 2024 and is expected to take 4 years (completion in October 2027) and is progressing on time and on budget.

Construction Update - October 2024

132 Avenue West (97 Street to 127 Street)

It’s the second year of 132 Ave Renewal West construction. Work will consist of reconstruction and paving of the roads, removal and replacement of public sidewalk, curbs, gutters and street lighting.

This year, the majority of construction will take place from 97 Street to 101 Street and from 107 Street to 113A Street. Please view this  scope map to see the 2024 construction area.

The work from 107 Street and 113 A Street has been completed, with the exception of sod and some tree plantings. The section between 112 Street and 113 A Street is now open.

The full road closures remain in effect for 107 Street to 112 Street.

Construction for 132 Avenue Renewal West began in spring 2023 and is expected to take 4 years (planned completion fall 2026). 132 Ave Renewal West is progressing on time and on budget.

132 Avenue East (Fort Road to 97 Street)

It’s the first year of the 132 Avenue Renewal East project. Work will consist of reconstruction and paving of the roads, removal and replacement of public sidewalks, curbs, gutters and street lighting.

This year, the majority of construction will take place from Fort Road to west of 68 Street. Please view this scope map to see the 2024 construction area. Work will also occur in the commercial business areas along 66 Street. 

Paving of the bike lanes has begun. The sidewalk, ramps, curb and gutter concrete pours will be ongoing, as required. Scopes of work on 66 Street are scheduled to be completed before the end of October. New traffic signals are now operational on 66 Street.

A full road closure is still in effect between Fort Road and 66 Street, with lane closures on 66 Street, as necessary. 

Construction on 132 Avenue Renewal East began in 2024 and is expected to take 4 years (planned completion October 2027). 132 Avenue Renewal East is continuing on time and on budget.

Project Update - November 2023

Neighbourhood Renewal construction in 132 Avenue Neighbourhood has wrapped up for the 2023 construction season! 

2023 construction began in June and will finish the first week of November. The 2023 construction season was a success and we completed all planned construction including: The reconstruction of roads, new sidewalks, curbs and gutters, Low Impact Development (LID) facilities, the new active transportation network and installed new street lights between 101 Street and 107 Street. 

There are some areas in the 2023 construction area that still require minor landscaping, concrete work and site furniture. Once the weather warms up, typically in early May, the landscaping subcontractor will be completing the topsoil and sod placement. By waiting until spring, the sod is more likely to establish. 

Collector renewal work will resume on 132 Ave between 101 Street and 97 Street and between 107 Street and 113 A Street in the second week of April 2024, weather permitting. The planned scope for 2024 will include the reconstruction of roads, new sidewalks, curbs and gutters, LIDs, new bike lanes and new streetlights. Prior to work resuming, construction notifications will be delivered to impacted residences. 

Thank you for your patience and understanding as we completed the first successful year of neighbourhood renewal construction. Construction on 132 Avenue began in spring 2023 and is expected to take five years.

Collector renewal on 132 Avenue is progressing on time and on budget.

The following routes will be detoured during construction: 106, 150X, 613, 624 and 625. Full detour information is available on Detours and Bus Stop Closures.

Preparing for Construction

Year 1 Construction Update - May 2023

Renewal work will start on 132 Avenue the first week of May 2023, weather permitting. 

The planned scope for 2023 will include:

  • Work on 132 Avenue from 97 Street to 107 Street (West)
    • This work includes a total closure of the street in both directions
  • View updated designs (12.36 MB) for 132 Avenue from 97 Street to 107 Street that will go into construction in 2023
  • This project consists of removal and replacement of existing road structure, addition of dedicated bike facility, boulevard sidewalk, new tree plantation, removal and replacement of existing street lights and signals, Low Impact Development on select locations, upgrade to businesses through corner store program and addition of new drainage infrastructure to accommodate continuous crossings as identified in the IFT drawings.

If you live in the construction area, you will receive an additional construction notice that provides more information on what to expect during construction prior to work beginning.

The City is expecting an increase in traffic volume and, as a result, an increased risk of speeding along roads connected to 132 Avenue as a result of construction.

To proactively maintain street safety, the City will be installing adaptable curb extensions along these routes in an effort to slow vehicles, shorten crossing distances and increase pedestrian visibility by preventing parking next to crossings.

Thank you for your patience and understanding as we start the first year of Renewal construction. Construction on 132 Avenue is expected to take 5 years.

Community Feedback on Final Design

Thank you to everyone who engaged with us during the Community Feedback on Final Design stage of the project. 

Online sessions were held from September 20 - October 12 and the online survey closed on October 13, 2022. We appreciate everyone who took the time to provide their feedback through the survey, emails and phone calls with the project team. 

The project team will review all of the feedback provided, along with technical information and City policies and programs, for consideration as we finalize construction drawings in preparation for construction in spring 2023.

Project Information

Final Design Detailed Information Package

Project Overview Video
This video demonstrates where we’ve come from and where we are currently at in the 132 Avenue Renewal Project.

What We Decided Report
Proposed Construction Staging

Final Designs

127 Street to 113 A Street (Kensington, Calder)
127 Street to 120 Street Final Design Plan
120 Street to 113A Street Final Design Plan
View the video

113 A Street to 97 Street (Rosslyn, Lauderdale)
113A Street to 107 Street Final Design Plan
107 Street to 97 Street Final Design Plan
View the video

97 Street to 82 Street (Glengarry, Killarney)
97 Street to 90 Street Final Design Plan
90 Street to 82 Street Final Design Plan
View the video

82 Street to 66 Street (Delwood, Balwin)
82 Street to 74 Street Final Design Plan
74 Street to 66 Street Final Design Plan
View the video

66 Street to Fort Road (Belvedere) 
66 Street to Fort Road Final Design Plan
View the video

Project Update - May 2022

Thank you to everyone who engaged with us during the Community Feedback on Draft Design stage of the project. We appreciate everyone who took the time to provide their feedback through the survey, the online sessions, emails and phone calls with the project team. 

The project team will review all of the feedback provided, along with technical information and City policies and programs, for consideration in the development of the final design, which will be shared in the fall 2022.  

What We Heard

View Project Information

Draft Design Information Booklet

Project Overview Video
This video demonstrates where we’ve come from and where we are currently at in the 132 Avenue Renewal Project.

Cost-sharing Opportunities
An opportunity for decorative street light upgrades.

Exploring Options and Tradeoffs - MA

Thank you to everyone who engaged with us during the Exploring Options and Tradeoffs stage of neighbourhood renewal. Online sessions were held from April 27 - May 6 and the online survey closed on May 20, 2021. The feedback you provided will be used to shape the draft design for 132 Avenue and the surrounding public and open spaces.

If you missed the opportunity to engage, you can still review information on the options and tradeoffs for driving, traffic calming, biking, parking and gathering spaces and community features:

Information Package

Video Presentation

What We Heard Report (June 2021)

For more information, please review the April 2021 issue of the 132 Renewal newsletter.

Building a Vision and Exploring Opportunities - November 2020

Thank you to everyone who engaged with us virtually during the Building a Vision and Exploring Opportunities stage of the project as we adjusted our engagement practices as a result of COVID-19.

The online survey closed on October 28, 2020 and we appreciate everyone who took the time to provide their feedback, including through paper copies of the survey, emails and phone calls received by the Project Manager. Your input is important as we begin to understand how you experience 132 Avenue and ask for your input on what we should do to make it better.

For more information on renewal, please review the September issue of the Building 132 newsletter.

What We Heard Report

Starting the Conversation - September 2020

Thank you to everyone who participated in the Starting the Conversation phase of 132 Renewal. In this phase, we asked the public to advise us on preferences for communication and possible barriers to participating in public engagement.

We have summarized the feedback received in a What We Heard document and we will be using this input to adjust our communications and public engagement plans moving forward.

What We Heard

Contact Us

Alban Ukshini

(Fort Road to 97 Street construction)

Title Delivery Project Manager

Email  alban.ukshini@edmonton.ca

Zahir Jarrar

(97 Street to 127 Street construction)

Title Delivery Project Manager

Email  zahir.jarrar@edmonton.ca

Building Great Neighbourhoods

All additional inquiries or escalations can be directed to the Building Great Neighbourhoods team by calling 780-496-4055 or through 311.

Email  BuildingGreatNeighbourhoods@edmonton.ca