aerial view of Terwillegar Drive

Terwillegar Drive is being upgraded to meet current and future needs. Construction started in 2021 and will take approximately 5 years to complete.

Program Status

Stage One

Stage 1 construction between Rabbit Hill Road and Whitemud Drive started in spring 2021 and was completed in 2024.

Stage Two

Stage 2 construction continues on the Rainbow Valley Pedestrian Bridge. Construction on the bridge began in the summer of 2023 and is anticipated to be completed in spring 2026. 

Stage Three

Early work construction on Stage 3, which includes building the head slope fills for both the new Terwillegar Drive roadway bridge and a new separated pedestrian bridge, has been completed. Completion of the head slope fills will allow ground settlement to occur before bridge construction begins in 2026.

Fall 2024 Newsletter

About the Program

Terwillegar Drive is a key north-south route connecting Edmontonians across the city. The road has exceeded its transportation capacity. To accommodate area growth, a three-stage plan has been approved to alleviate congestion and provide all users a safe and efficient route.