Base inspection costs are included in permit fees. See Additional Fees for more information on costs for additional inspections.
Fees listed below apply to both stand-alone HVAC permits and HVAC permits obtained in connection with a building permit.
New Construction
2024 fees effective January 1, 2024
Project Type |
HVAC Permit Fee |
Minimum Fee |
Safety Codes Fee |
New commercial, industrial, institutional, multi-residential development |
$0.58 per $1,000 construction value |
$180 |
4% of the permit cost with a minimum of $4.50 and maximum of $560 |
Altering or Replacing an Existing System
2024 fees effective January 1, 2024
Project Type |
HVAC Permit Fee |
Safety Codes Fee1 |
Total |
Commercial building |
$180 per unit or address |
$7.20 |
$187.20 per unit or address |
Multi-unit residential building |
$115 per unit or address |
$4.60 |
$119.60 per unit or address |
(1) Construction value is defined as the total cost of materials and services. Construction value does not include: landscaping, parking lots, sidewalks, furnishings, appliances, interior window coverings, temporary service connections, insurance or bonding, interim financing, permit fees, professional consulting fees, GST.
(2) Safety code fee is 4% of the permit cost with a minimum of $4.50 and a maximum of $560.00.
For more information see the
2024 Planning and Development Fee Schedules
, effective January 1, 2024.