South LRT Project History
October 2010 |
Ellerslie Road to 41 Avenue SW Concept Planning ApprovedConcepts plans for the 3 km extension from Ellerslie Road to 41 Avenue SW have been brought up-to-date with the Neighbourhood Area Structure Plans for Heritage Valley Town Centre and Desrochers. These plans were approved by City Council in October 2009 and October 2010. |
May 2010 |
Century Park to Ellerslie Road Preliminary Engineering CompletedPreliminary Engineering for the first 4.5 km from Century Park to Ellerslie Road was completed in 2010. |
April 2010 |
Information Session |
March 2010 |
Stakeholder Information Panel Wrap Up
|
December 10, 2009 |
SIP Meeting |
October 2009 |
Open House |
September 24, 2009 |
SIP Meeting |
August 2009 |
Residential Land Owner and Business Owner/Operator Meeting |
July 2009 |
Fact SheetPreliminary Engineering Fact Sheet |
March 2009 |
Ellerslie Park and Ride Open HouseShared information with local residents about a potential temporary Park and Ride at Ellerslie Road.
Having evaluated the temporary Park and Ride against other options, the City decided to proceed with a permanent Park and Ride facility at the Ellerslie Road/127 Street location. A temporary Park and Ride at the Century Park LRT station will provide service to commuters while the facility at Ellerslie Road is constructed. |
July 8, 2008 |
Edmonton City Council approved Concept PlanCity Council approved the South LRT Extension from Century Park to the south City limit. |