Main page content begins here

Project Lifecycle Build

Project Timeline

  • Concept design β€” spring 2015
  • Design completion β€” 2016/2017
  • Construction start β€” 2018

Construction Updates

​In order to facilitate construction on new boat docks and launch locations at Dawson Park, Hawrelak Park and Laurier Park, a section of trees at each location, beginning with Laurier and Hawrelak parks, will be removed. Removal of the trees at all three locations will be wrapped up by March 9, 2018. City-owned trees are a highly valued asset and are only removed when all other preservation options are unsuitable.

Construction on most of the boat docks and launch locations will begin in spring 2018.

Construction of Whitemud Park will begin once an alternate site is found upstream of Whitemud Creek.

Construction of Emily Murphy Park will be done as part of the Groat Road Bridges project once bridge rehabilitation is complete.

Laurier Park:  Mid-July to the end of October 2018

Project involves construction of a new seasonal floating dock and a new viewing deck on the river bank.  Closures to the launch ramp related to construction are not expected at this time.  Gravel trail detours will be required, please respect and follow all signage.

Hawrelak Park:  Mid-July to the end of October 2018

Project involves construction of a new seasonal floating dock, retaining wall and viewing area. Temporary gravel trail closure may be required during the work; please respect and follow all signage.

Dawson Park:  Mid-July to the end of October 2018

Project involves construction of a new seasonal floating dock, regrading the trail to the river and construction of a retaining wall.  Full trail closures are expected during construction for public safety. Please respect and follow all signage.

50 Street/Capilano Park:  August 20 to September 18, 2018

Project involves construction of a new seasonal floating dock and expansion of the concrete launch ramp. Closure of the full launch site is expected during construction for public safety. Please respect and follow all signage.

Whitemud Park:  Timeline to be determined once approved by City Council

Project involves construction of a new seasonal floating dock and a short gravel trail to the river. Detours to the adjacent trails may occur. Please respect and follow all signage.