Arena: (81.89KB)
Rink D refrigeration floor preparation - Sep/10
Arena: (91.98KB)
Exterior view of Rink D siding installation and parking lot asphalt - Sep/10
Arena: (93.57KB)
Forming and pouring of exterior concrete plinth - Sep/10
Arena: (108.24KB)
Installation of refrigeration lines in Rink C - Sep/10
Arena: (98.53KB)
Installation of overhead lighting in Rink A - Sep/10
Aquatic Centre: (87.95KB)
5 metre diving platform and stairs poured - Aug/10
Arena: (115.05KB)
Exterior Siding Application to Rink D - July 20/10
Flexi Hall: (89.52KB)
Structural Steel Ceiling Support Installation - July 20/10
Tot Pool (98.68KB)
Tile Application - July 20/10
Fitness Centre (115.73KB)
Structural Tree Paint Application - May 13/10
Arena Complex (103.43KB)
Structural Steel Erection North View - May 13/10
Arena (74.66KB)
Rink #1 Spectator Seating Concrete Formwork - April 6/10
(46.64KB)
Whirlpool Tile Application - March 9/10
Flexi Hall (56.34KB)
Exterior Metal Siding Installation - March 9/10
Arena (75.46KB)
Under Slab Heating Line Installation
Arena (110.58KB)
Structural Steel Erection over Pad 1 - Dec 1/09
South Parking Lot (66.98KB)
Asphalt, Curbs, Gutters and Lighting Installed - Nov 2/09
South Entrance (102.64KB)
Exterior Tinderstone Installation - Nov 2 2/09
Arena (62.75KB)
Construction of Dressing Rooms between Pad 1 & 2 - Sept 29/09
Arena Complex (149.59KB)
Refrigeration Header Pipe Installation - Sept 15
Arena Complex (93.06KB)
Concrete Slab Work for Ice Rinks 1 & 2 - Sept 8/09
Arena Complex (61.37KB)
Dressing Room Concrete Formwork - Sept 8/09
Arena Complex (149.28KB)
Refrigeration Header Pipe Installation - Aug 31/09
Arena Complex (79.15KB)
Concrete Formwork and Insulation - May 20/09
West Entrance (164.31KB)
Aug 19/09: Structural Steel Installation
South Entrance (74.53KB)
Aug 19/09: Canopy Installation and Laying of Drop Off Loop Asphalt
53m Pool (71.77KB)
July 21/09: Pool Deck Concrete Poured
Teach Pool (69.28KB)
June 16/09: Mechanical Rough-in Prior to Concrete Placement
Amphitheatre (87.58KB)
June 16/09: Formwork in Preparation for Concrete Pour
Aquatic Centre (116.55KB)
June 16/09: Leisure/Wave Pool Structural Steel Erection
Social Heart (81.17KB)
May 26/09: Preparing for the Structural Slab Pour
Whirl Pool (54.54KB)
May 20/09: Concrete Basin with Pool Fittings Installed
2nd Floor Mezzanine (85.94KB)
May 12/09: Walking/Jogging Track and Social Heart Structural Framework
Flexi Hall (42.65KB)
May 12/09: Interior View with Structural Slab Poured
Flexi Hall (38.10KB)
May 12/09: Masonry and Steel Deck Installed, Roofing to Commence
Teach Pool (68.75KB)
May 12/09: Mechanical Installation Prior to Concrete Placement
Flexihall (81.02KB)
Mar 31/09: North view - Structural framing
Flexihall (101.00KB)
Mar 31/09: Preparation for Concrete Floor Placement
Flexihall (79.24KB)
Mar 31/09: Applying roof deck and masonry wall installation
Flexihall (111.68KB)
Mar 17/09 View of Flexihall from future drop-off loop.
Multi-Purpose Pool (59.30KB)
Mar 3/09: View of the 53 pool with flexihall in the background
Flexihall (96.21KB)
Feb 17/09: Flexihall structural steel installation
Whirlpool (100.80KB)
Feb 17/09: Reinforcing steel associated with the whirlpool
Flexihall Roof (62.59KB)
Feb 6/09: First section of the roof structure being placed
Pool Formwork (62.82KB)
Feb 3/09: Concrete formwork for teach and wave pool
Changerooms (89.78KB)
Feb 3/09: Main floor changerooms concrete floor
Concrete Floor (127.13KB)
Oct 28/08: Lower mechanical room, concrete floor placement
Pool Basement (63.24KB)
Sep 30/08: Excavation in preparation for pile installation
Flexihall (47.07KB)
Sep 30/08: Concrete forming for exterior wall and storage