Borden Park Revitalization Plan

Borden Park has served Edmonton's families for 100 years.

We are working on a revitalization plan that will see Borden Park's legacy continue for many years to come.

Borden Park Concept Diagram

Project Timeline

2012

Winter:

  • General site demolition and removals for: playgrounds (x2), wading pools (x2), asphalt, site fixtures, water taps, fountain & planters

Spring/Summer:

  • Construction of work including : concrete walkways, playgrounds (x2), shelters, site furniture, formal garden, fountain, parking lot realignment, tree planting, tree removal and public art installation.
  • Construction of the Park Pavilion
  • Construction for Bandshell Refurbishment